St Helena Tunnel

From Infogalactic: the planetary knowledge core
Jump to: navigation, search
St Helena Tunnel
File:St helena tunnel.png
St Helena tunnel on opening day (18 December 2015)
Overview
Location Ewingsdale, New South Wales, Australia
Status Open
Route Pacific Highway
Operation
Work begun 27 September 2012
Opened 18 December 2015
Owner Roads & Maritime Services
Traffic Automotive (Cyclists and Pedestrians in side lane)
Character Motorway
Technical
Construction Lend Lease
Length 434 metres (1,424 ft)
Number of lanes Built for 3 lanes each direction, opened as 2 northbound & 3 southbound lanes
Operating speed 110 km/h[1]
Tunnel clearance 5.3 m
Width 13.3 m
Grade 2.2%
File:St Helena Hill Tunnel - Looking south - Under Construction on 14-02-23.jpg
Looking south from St Helena Hill, the construction compound, site office and machine maintenance area at the southern portal of the tunnel (23 Feb 2014)
File:Tunnel-south-southern.jpg
Close up southbound tunnel southern portal under construction (22 April 2015)
File:St helena tunnel interior.jpg
Interior of the tunnel (26 November 2015)
File:St helena tunnel night.jpg
Tunnel at night hours from opening(18 December 2015)

The St Helena Tunnel is a twin-tube road tunnel under St Helena Hill in the locality of Ewingsdale, near Byron Bay, New South Wales, Australia. The tunnel was built as part of the 17 km Tintenbar to Ewingsdale upgrade of the Pacific Highway, which involved a new alignment of the highway.

The tunnel was built to avoid the steep grades of St Helena Hill on the previous alignment of the highway, and the associated heavy truck noise and pollution. It is 434 m (1,424 ft) long and at its deepest point is 45 m below the 131 metre high ridge line. There are two tunnels, with the northbound tunnel accommodating two traffic lanes and the southbound three traffic lanes, due to the gradient of the highway at this point. There is also a bicycle/pedestrian lane in each tunnel. [2]

The cost of the Tintenbar-Ewingsdale upgrade project was $862 million, jointly funded by the New South Wales and Federal governments. It opened on 18th December 2015. The remaining tie in work at each end was completed in March 2016.[3][needs update]

Milestones

  • January 2010 - Planning approval and construction funding for the Tintenbar to Ewingsdale project including the St Helena Tunnel.
  • May 2010 - NSW Roads and Maritime Services called for expressions of interest for the construction of the upgrade
  • December 2010 - three companies were invited to submit detailed tenders
  • August 2011 - the contract was awarded to Lend Lease (previously Baulderstone).[1][4]
  • 27 September 2012 - the shovel ceremony was held to commemorate the start of construction.
  • 28 May 2013 - Blasting began on the twin tunnels.
  • 24 January 2014 - Excavator broke through on the northbound tunnel[5]
  • 26 February 2014 - Excavator broke through on the southbound tunnel
  • December 2015 - Commissioning of tunnels began
  • 18 December 2015 - The highway upgrade, including the twin tunnels, opened to traffic.

See also

References

  1. 1.0 1.1 Lua error in package.lua at line 80: module 'strict' not found.
  2. Lua error in package.lua at line 80: module 'strict' not found.
  3. Lua error in package.lua at line 80: module 'strict' not found.
  4. Lua error in package.lua at line 80: module 'strict' not found.
  5. Lua error in package.lua at line 80: module 'strict' not found.

External links

Lua error in package.lua at line 80: module 'strict' not found.